Description
When creating activities, the only way in which daily effort is set correctly is if you select the level of effort in hours.
If it is set in days, effort is multiplied by 3 and by 4 if it is set in months.
For example, if I create an activity with start date, 2 days effort and no end date, it will take 6 days with 8 hours per day
If I set 2 days effort with end date two days later, each day will have 16 working hours.
If I set an activity with start and end date two weeks later, with no level of effort, task is set to one hour effort per day, instead of eight.
Could you please clarify this issue?
Solution
A solution hasn't been entered
File Attachments
There are no file attachments
Ticket Activity
Date | Event |
---|---|
Matt Rajkowski 3/15/2008, 10:15 AM | [ Ticket Opened ] |
Matt Rajkowski 3/15/2008, 10:15 AM | [ Ticket is unassigned ] |
Matt Rajkowski 3/15/2008, 10:15 AM | [ Priority set to Scheduled ] |
Matt Rajkowski 3/15/2008, 10:15 AM | [ Severity set to Normal ] |
Matt Rajkowski 3/15/2008, 10:23 AM | Is this in the Project Graphs that you see the incorrect values? |